Power Plant Maintenance, Rehabilitation
& Overhauling (MRO) Contracts

1983-1993

JOHN BROWN ENGINEERING, UK

Rehabilitation & Spare Parts Supply for Various GE Frame-5 GT of BPDB

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • GT Capitals & HGPI Components Refurbishment

  • Power Plant Overhauling & Rehabilitation

  • Logistic Support

  • Gas Turbine Control Systems

1984-1996

ELBAR BV of The Netherlands

Refurbishment of Hot Gas Path Components of various GT Power Plants of BPDB

  • Contract Procurement

  • GT Capitals & HGPI Components Refurbishment

  • Logistic Support

1985

ABB - ASEA BROWN BOVERI, Switzerland

Supply of Hot Gas Path Components for BPDB Power Plants

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • Logistic Support

1987

WESTINGHOUSE SERVICES, Singapore

Rotor Repair & Rehabilitation for BPDB Power Plant

  • Contract Procurement

  • GT Capitals & HGPI Components Refurbishment

  • Rotor Refurbishment

  • Power Plant Overhauling & Rehabilitation

  • Logistic Support

  • Gas Turbine Control Systems

1990

F.R. TULK, Australia

Overhauling of Unit-3 at Karnafuli Hydro Power Station of BPDB

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • Power Plant Overhauling & Rehabilitation

  • Logistic Support

  • Gas Turbine Control Systems

1993-1997

KVAERNER ENERGY, UK

Rehabilitation & Spare Parts Supply for various GE Frame Size GT of BPDB

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • GT Capitals & HGPI Components Refurbishment

  • Power Plant Overhauling & Rehabilitation

  • Logistic Support

  • Gas Turbine Control Systems

1999

KVAERNER ENERGY, UK

Conversion of Single Fuel System to Dual Fuel of Baghabari 71 MW, BPDB

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • GT Capitals & HGPI Components Refurbishment

  • Power Plant Overhauling & Rehabilitation

  • Logistic Support

  • Gas Turbine Control Systems

2000

MJB INTERNATIONAL, Dubai

Rehabilitation of 71 MW GE Frame-9B Gas Turbine of Baghabari, BPDB

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • GT Capitals & HGPI Components Refurbishment

  • Power Plant Overhauling & Rehabilitation

  • Logistic Support

  • Gas Turbine Control Systems

2001

Rehabilitation of 20 MW GE Frame-5 Gas Turbine of Sylhet Power Plant, BPDB

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • GT Capitals & HGPI Components Refurbishment

  • Rotor Refurbishment

  • Power Plant Overhauling & Rehabilitation

  • Logistic Support

  • Gas Turbine Control Systems

2007

Rehabilitation of 30 MW GE Frame-6 Gas Turbine of Shahjibazar, BPDB

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • GT Capitals & HGPI Components Refurbishment

  • Rotor Refurbishment

  • Power Plant Overhauling & Rehabilitation

  • Logistic Support

  • Gas Turbine Control Systems

2016-2017

Rotor Refurbishment & Major Inspection of Frame-6B GT of Venture Energy

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • GT Capitals & HGPI Components Refurbishment

  • Rotor Refurbishment

  • Power Plant Overhauling & Rehabilitation

  • Logistic Support

  • Gas Turbine Control Systems

2018

Major Overhauling of 20 MW GE Frame-5 GT of Sylhet Power Plant, BPDB

  • Contract Procurement

  • Power Plant Overhauling & Rehabilitation

  • Logistic Support

  • Gas Turbine Control Systems

2018

Major Inspection (MI) and Spares for Rangpur GT Power Station, BPDB

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • Logistic Support

2019

Procurement of MI Spares for GT Unit-1 & 2 of Barishal GT Power Station, BPDB

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • Logistic Support

2019

Procurement of Spare Parts & Accessories of Rangpur GT Power Station, BPDB

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • Logistic Support

2020

Major Inspection & Casing Replacement of Rangpur GT Power Plant, BPDB

  • Contract Procurement

  • Power Plant Overhauling & Rehabilitation

  • Logistic Support

  • Gas Turbine Control Systems

2021

Procurement of Hot Gas Path Components of Shahjibazar 60 MW Power Station, BPDB

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • Logistic Support

2022

Combustion Inspection (CI) and Spare Parts of Fenchuganj CCPP, BPDB

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • Logistic Support

2022

Procurement of Bearings of GE Frame 9E GT of Chandpur 150 MW CCPP, BPDB

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • Logistic Support

2024

Schedule Maintenance, CI Spares of Shahjibazar 60 MW Power Station, BPDB

  • Contract Procurement

  • GT Capitals & Spare Parts Support

  • Logistic Support